- Ensure the technical integrity and proper installation, and do all the necessary tests to obtain the best efficiency to the operation system:
- Pre- commissioning & commissioning and start –up of all type of motors LV & MV.
- Pre- commissioning & commissioning of M V & L V switch gear.
- Commissioning and adjusting protection settings of all MCCB and MLP (S.C and MLP, including thermal (O.L, G.F, U.V / O.V, UBC and etc.) for 0.4 K V low voltage distribution (Motor control center).
- Testing, commissioning and energize transformer up to 340 MVA.
- Testing, commissioning of ISO phase Bus duct between generator and excitation transformer & main transformer.
- Pre- commissioning & commissioning of all types of local control panel and level control switches.
- Pre- commissioning & commissioning of all cables.
- Perform the commissioning tasks including preparation of commissioning plans, pre-functional checklists and test procedures; performing construction inspections, testing equipment and systems, and writing report.
- Perform and troubleshoot activities at location to diagnose problems, determine appropriate resolution and implement corrective actions.
- Review client QC requirements and ensure that quality control documentation for a project meets contractual requirements till handed over to the client.
- Review and participate in ITP’s preparation to ensure their covered all activities and meet with the vendor and contractual requirements.
|
Handed Over all TOP’s, Commissioning Book & special tools to the client.